10,249 views
Contract signed on December 7, 2022 with the Webuild SPA Association – Impresa Pizzarotti&C SPA Duration: 6 months design 36 months execution Building authorization received in May 2024 The contract provides for the development of the technical project and the execution of electrification and modernization of the railway infrastructure and superstructure for the maximum speed of 160 km/h on the Alesd – Frontier section Length of 46.74 km 2 new underpasses, at Tileagd and Oradea, doubling the line on 18 km