Contract signed on December 7, 2022 with the Webuild SPA Association – Impresa Pizzarotti&C SPA Duration: 6 months design 36 months execution Building authorization received in May 2024 The contract provides for the development of the technical project and the execution of electrification and modernization of the railway infrastructure and superstructure for the maximum speed of 160 km/h on the Alesd – Border section Length of 46.74 km 2 underpasses us, in Tileagd and Oradea, the doubling of the line for 18 km A like and share always helps If you want to contribute to the making of these films or to find out new information behind them and more Join us! ???? / @marrinul You can also find me on: Patreon: https://www.patreon.com/user?u=84234114 / marin.marian.m ???? [email protected]