In the area around the old Oosterweel church in the harbour, work is in full swing. Over the next year and a half, we will be building no less than 3 km (!) of walls deep in the ground to demarcate the construction pit - say 7 construction pits - so that the Oosterweel junction can be built dry. In order to make room for these construction pits, our contractor has carried out a lot of work in recent months, such as filling in part of the Noordkasteelvijver, relocating cables and pipes and redesigning the traffic. In this webinar, Gerlinde will bring you up to date again using beautiful aerial images from our contractor TM Rinkoniên*. *The TM Rinkoniên Oosterweelknoop contractor consortium consists of the contractors Artes, CIT Blaton, Mobilis, Boskalis and Stadsbader.