The process of installing electric cables underground in an apartment by digging a hole with a 200-t

278,952 views

EBS Documentary

Published on Jan 25, 2024
About :

※ This video is part of <Extreme Job - Power Plant Construction 1-2> broadcast from April 14-15, 2010. If a new city is built on a wasteland, what would be the most necessary living infrastructure? One thing that everyone would agree on is 'electricity'. From household use to industrial and commercial use. The influence of electricity on our daily lives is a fact that everyone knows without needing to list it all! However, there are those who have gone underground to light up the ground. They are the so-called 'power plant construction crew' who dig tunnels to bury underground electrical facilities such as towers, high-voltage lines, and utility poles that are tangled like spider webs and spoil the cityscape. As the size of the city grows and the power supply increases, these people struggle to provide a safe and smooth power supply, going back and forth between the ground and underground. We meet the power transmission line construction crew who are willing to smile even at extreme work when they think that the wires they made with their own hands will light up the night of Korea. - Those who went underground to light up the city - Messer Shield Inside the tunnel, which is so low that one person can barely stand upright. 10 meters underground, the narrow tunnel where not a single ray of light enters is an underground construction site to supply additional electricity to the industrial complex! However, the tunnel is so narrow that they cannot use excavation machines and must dig only with manpower. As a result, the amount of thrust that can be excavated in a day is only 40 centimeters. Furthermore, the only equipment used to drill into the rock is a small machine! Therefore, in order to finish the construction period on time, it is difficult work that must be done day and night in two shifts 24 hours a day, but we go into the extreme site where they endure dust and noise in a closed tunnel for more than half a day! - Unpredictable extreme rock appears! Find a solution! A solid rock appears in front of them as they were digging the ground with an excavation machine. The main character of the solid rock that stopped the excavation work is an extremely hard rock that is difficult to drill with a normal excavation machine. An emergency meeting was called among the workers, and they decided to break the rock using gunpowder blasting. However, another obstacle was encountered! There are about 10 types of underground facilities buried within a 5m section right above the tunnel site! Gunpowder blasting can cause a major accident, so they decide to do a weak blasting test. Will they be able to successfully complete the blasting and resume work? - The first step to undergrounding, drill a vertical shaft 30m underground! A huge hole with a diameter of 10m is drilled in the middle of the city. It is a 'vertical shaft' that will connect the surface and the underground during underground work. If you go down the stairs 30m underground, you can see people working on the excavation while wearing helmets and masks. Since they are drilling through solid rock, noise and dust are a given! Since it is underground where it is difficult to leave once work begins, they have a unique way of lowering a rope from the surface even when eating snacks! After a short but sweet snack break, the workers resume their work. We visit the work site where the vertical shaft is dug under the vertical shaft where the lights are on 24 hours a day. - Safely transport the 200-ton, super-large excavation machine! - A construction site in Busan where the shield TBM vertical shaft work is finished and a total of 2km of tunnel excavation is about to begin. Suddenly, an urgent siren sounds. This is because the excavation machine weighing over 200 tons is coming into the 30m underground tunnel. Since it is an expensive piece of equipment worth several billion won, which is rare in Korea, as well as its enormous weight, moving it takes time. This requires advanced technology and specialized knowledge. Will they be able to finish installing it safely? An unexpected situation! The excavation machine suddenly stops! The people working in the vertical shaft check the work situation inside the tunnel through the walkie-talkie that receives the aboveground and underground. After exchanging walkie-talkies, the site supervisor suddenly becomes busy and urgently goes up to the ground where the machine control room is to check the situation. There is a mysterious defect in the machine that transports the soil that comes out when digging the tunnel! If work continues like this, damage to the excavation equipment worth billions of won may occur, so they decide to stop the machine work immediately. To make matters worse, unexpected rain pours down on the site. Will they be able to resume work quickly? - The final stage of the underground cable work, cable finishing work! The final stage of underground work! Today is finally the day when t

Trend Videos
11:06
605,389 views   7 days ago
11:34
1,960,203 views   12 days ago
10:21
4,057,511 views   9 days ago
58:52
553,834 views   5 days ago
3:59
M2
932,862 views   1 day ago
8:05
2,017,176 views   2 days ago
3:11
44,128,421 views   6 days ago
Google AdSense
336 x 280
Up Next
10:31
Ridddle AR
75,069 views
3 years ago
11:10
Ridddle AR
224,364 views
3 years ago
14:06
THE HORROR - مهند السيوف
5,317,163 views
3 years ago
10:22
Mazen - مازن
202,105 views
21 hours ago
46:08
الجانب المُشرق | Bright Side Arabic
69,352 views
1 year ago
26:27
عبدالمحسن MSG
804,694 views
7 months ago
10:48
Nest Productions
489,231 views
4 years ago
12:53
الجانب المُشرق | Bright Side Arabic
2,251,806 views
5 years ago
12:28
Galaxeeco
179,639 views
4 months ago
11:50
36:18
Ahmed Elbadawy
105,882 views
2 days ago
1:15:08
يلا وثائقيات
91,386 views
1 day ago
14:00
Ridddle AR
190,430 views
3 years ago
17:01
Galaxeeco
412,252 views
1 year ago
15:50
Barhom m3arawi - برهوم معراوي
449,976 views
19 hours ago
9:23
عشوائيات
107,134 views
5 days ago
10:05
24:12
33:29
26:54
26:16
CarAntiLab
37,387 views
2 weeks ago
20:47
erbos cz
29,150 views
3 years ago
30:56
35:37
CestujKlasikou
51,401 views
3 years ago
24:31
erbos cz
28,260 views
1 year ago
28:01
erbos cz
42,065 views
4 years ago
18:51
erbos cz
21,357 views
4 years ago
28:38
erbos cz
138,540 views
4 years ago
27:33
TECH kanál
4,540 views
3 years ago
19:08
CestujKlasikou
77,706 views
4 years ago
28:07
Autoklempíř Brandýs
91,974 views
4 years ago
26:44
17:49
18:42
CestujKlasikou
48,993 views
4 years ago
Google AdSense
336 x 280

fetery.com. Copyright 2024