7,562 views
#up-date #4 - of the road junction works between #A0 and DN2 #2023 #2024 September 17, 2024 #2024 - Up date previous September 3, 2024 #LOT 3 #NORD #autostrada #A0 Afumati - Pantelimon -Caldararu-Cernica Activity on site: Good activity with visible progress! Works 7 Months from the Start of the construction period: the bridge piles over DN2 are working well E85 the future pillars came out of the ground, more machines were brought, more workers Lot 3, DN2 (Afumati) - DN3 (Cernica), 8.6km, under construction. Builder selected in November 2022: China Civil Engineering Construction Corporation, price 397,996,117.63 lei without VAT, design duration: 12 months, execution duration: 18 months. Contract signed in March 2023 #djimini2 #dji #djimini2 #construction #bridge #aerial #autostrada #centuraA0 #UMB #viaductcernica #new #4k #1ksub #1k #peundemerg #cnair #2024