179,242 views
Construction of a foundation slab for a 6 by 8 meter house. The process from soil development to concreting. The work was completed in three days. On the first day, a crushed stone sand cushion was installed with layer-by-layer compaction. On the second day, EPPS was laid according to the level and the lower mesh was reinforced. On the third day, the upper mesh of the slab was reinforced, the formwork was unfastened, and concreting was done. The work was completed independently and alone) During concreting, the customer helped to stretch the concrete over the slab, for which we thank him very much! Watch! Subscribe! Comment! Like! Instagram: / dmitrievstroy96.ru Support the builder: https://www.donationalerts.com/r/dmit... #construction #foundation #foundationplate #reinforcement #concreting #dmitrievstroy96 Creative Commons Attribution 4.0 license for the use of the track Green Daze (artist: Audionautix): https://creativecommons.org/licenses/... Artist: http://audionautix.com/